What follows is The Northway and the Adirondack Forest: A Highway Location Study, published August 31, 1957 by the New York State Department of Public Works. The 333.49-mile-long Adirondack Northway, Interstate-87, has origins in the construction of the Major Deegan Expressway in the 1930s and was completed to the Canadian border in 1967.
The Northway (Interstate Route 502 [now designated I-87]) gets its name by traversing the area once known as the “Great Northern Wilderness.” Vital to the national defense network, it is being designed and constructed in accordance with the Federal Aid Highway Act of 1956 as a joint Federal-State venture.
Stipulations of the Bureau of Public Roads of the U.S.Department of Commerce require that Interstate routes be as direct as the terrain permits and that they have access which is controlled, or limited, to specific points.
As controlled access highways, the Interstate System will supplement but will not supplant existing highways. Also, if the right-of-way of an existing highway is used for the Interstate route, a new road must be constructed for the service of lands along the preempted highway.
The valleys of the Adirondack region are narrow and closely confined by the area’s rough and irregular mountains. Few are wide enough to accommodate both an Interstate highway and another satisfactory road without the construction of extensive retaining walls and bridges, and the relocation of stream channels. This would be economically unsound. For these reasons, all of the alternate routes studied, of necessity touch on the Adirondack Park area in one or more locations.
Highway design has made rapid strides since the day when an unsightly notch might have been hacked in the crest of a ridge, or a broad highway laid on a shelf gouged out of the side of a slope. Even since the beginning of the recently-constructed New York State Thruway, design standards have improved.
Multiple lane divided highways are now designed as two separate roadways with the median strip left in a pleasing natural condition. In rough country, this is generally the cheapest method of construction, also the safest and most pleasant to the driver.
The objective of the designers is to make all Interstate routes in New York examples of ideal construction with a minimum dislocation of economic and natural features.
That portion of the route which passes through the Forest Preserve will be designed with two separate roadways. Median strips will vary from to 200 feet in width. Existing roads will be separated from the Interstate route and no access to the Forest Preserve will be provided which is not available now on existing roads.
The Northway
Cuts and fills will be held to the minimum compatible with acceptable grades, and slopes will be planted with native trees and shrubs. There will be a minimum of clearing and selective cutting of trees – especia11y in the median area. The result will be a highway with parkway characteristics offering scenic views uncluttered with commercialization.
In addition, deer crossings will be discouraged by the erection of adequate fences. Fire lanes will be maintained adjacent to the roadways and the road itself will serve as an effective fire break. Along those portions of the route not within Forest Preserve land but within the Adirondack Park area remnant parcels will be made available as a part of the Preserve.
A route has been selected which is the most economical both in terms of construction costs, and damage to private property. What damage will it do to the Forest Preserve? Very little, if any. A few years after the slopes have been planted and the vegetation has grown, these slopes will have returned to their natural state.
Roadside scenery will not be marred by billboards, hot dog stands, gas stations or motels. Instead motorists will be treated to such splendid new views of the forest lands that many more visitors will be attracted to the Adirondack area.
The Federal Bureau of Public Roads requires a minimum right-of-way width of 250 feet for a four-lane divided highway. Until the actual center line of the Northway is surveyed in the field and the lines marking its boundaries are located on the ground the exact degree of land-taking cannot be determined.
From available maps it is estimated that the total length of Forest Preserve lands traversed by the route is less than 25 miles and approximately 400 acres. This includes the areas west of Port Henry and south of Elizabethtown as well as the portion around Schroon Lake. Less than half of the acreage acquired will be involved in actual construction and balance will remain undisturbed.
The Study
This report covers the preliminary alternate route studies for Interstate Route 502 from Warrensburg to Schroon Falls – a distance of about 30 air line miles. It includes brief route descriptions with location advantages and disadvantages; a contour map showing alternate routes and forest preserve lands; ground line profiles of the four routes studied; and typical cross sections.
The profiles are not intended for the purpose of developing highway grades, but rather to indicate the comparative elevations and roughness of the various routes.
Preliminary Studies for Interstate Route 502: Warrensburg – Schroon Falls
The proposed location for the Interstate Route 502 from Albany to Warrensburg lies in the wide Hudson Valley near existing Route 9 in order to serve areas already developed and those expected to expand in the future.
North of Warrensburg, present Route 9 traverses some very rough terrain, through narrow passes and around mountain peaks. For this reason, it became necessary to find a new location for the Interstate route. Four possibilities were plotted on U.S.Geological Survey sheets, profiles drawn up, and field reconnaissance trips were made.
As a result of these studies, line A (the western route) and line D (the eastern route) were eliminated from further consideration. Lines B and C still looked feasible, so aerial photos and photogrammetric maps (scale 1 inch = 400′) were made to allow for more detailed studies.
The degree of roughness was determined for each route by adding the total rise and fall of terrain along the proposed alignment.
(Note: A fifth route possibility was discarded after preliminary examination of U.S. Geological Survey sheets. This route east of Lake George would have by-passed the Forest Preserve. Numerous high mountain ranges made it impractical. In Chart references it is referred to as Route X.)
Design Standards
The standards call for two 24-foot roadways separated by a variable median with a minimum width of 44 feet. Shoulders will be 10 feet wide at the outer edge of the pavement and 6 feet wide on the median side. The horizontal alignment will be limited to 3-degree maximum curves and will in general conform to the natural terrain.
Grades will have a desirable limit of 3 percent wherever reasonable cuts and fills will permit. However, an absolute limit of 5 percent will be
held where extremely rough topography indicates the necessity to exceed the desirable grade in order to keep within practical economical limits.
Alignment A, 37.7 Miles
This route continues northwest from Warrensburg following the Hudson valley to a point three miles east of North Creek, then northeast along the west bank of Trout Brook to a point just west of existing Route 9 near the village of Schroon Falls.
There are many difficulties and disadvantages in trying to develop a route along this line. The route is about six miles longer than the shortest route studied, and veers away from much of the development in the area; thus offering very poor service for local usage.
For several miles both north and south of the village of Riparius the mountains drop off sharply to the Hudson River requiring extremely difficult and expensive construction.
This route would pass over a rather high mountain range with about nine miles exceeding an elevation of 1,000 feet, and at one point reaching an elevation of 1,480 feet above sea level. Total rise and fall is 3,510 feet. Because of the above undesirable features this route was considered not acceptable.
Alignment B, 32.0 Miles
This route continues north from Warrensburg up the west bank of the Schroon River to a point near Pottersville, then northerly along the west side of Schroon Lake and Route 9 to Schroon Falls. This route is about one-half mile longer than Route “C”.
In traversing the west side of the Schroon River it would require heavy cuts and fills near South Horicon, because of the steep mountain dropping into the river. This problem might be overcome by using the east bank of the river but the advantage would be lost because of the requirement for an expensive structure across the river north of South Horicon.
Along the northern portion of the route it is necessary for the expressway to either traverse expensive tourist development or to be shoved back against steep hillsides where construction is difficult and expensive. It has approximately three miles of highway at an elevation of over 1,000 feet with a maximum elevation of 1,170 feet.
One of the major criticisms of this route is the frequency of rises and falls caused by climbing over several mountains. Total rise and fall is 4,970 feet. It would include six miles of grades over 3 percent and three miles of grades at 5 percent.
There would be a total length of eight miles of cuts and fills exceeding 20 feet. These heavy cuts and fills and steep grades not only add greatly to the initial cost but also increase the cost for maintenance and mar the natural terrain.
If the above figures are compared with alignment “C” it will be found that the latter appears to possess advantages in practically all considerations, and on this basis line “B” became a secondary choice.
Alignment D, 34.0 Miles
This route continues north from Warrensburg up the west bank of the Schroon River to Starbuckvilie, then follows the west shore of Brandt Lake [sic] continuing along the east side of Desolate Brook to a point near Alder Pond, then westerly to Severance and again northerly to Schroon Falls.
There were several problems and some disadvantages foreseen in attempting a route along this alignment. The route is about 2 1/2 miles longer than the favored route “C” and bears several miles east from possible future development along Schroon Lake.
The mountains bordering Brandt Lake drop off so sharply to the lake that very expensive and difficult construction would be required. The mile long swamp near the origin of Desolate Brook, with the narrow valley and steep mountains on either side, presented not only expensive and impractical construction but a highway through such terrain risks possible future pavement failure.
About four miles of this route is over 1,000 feet in elevation. Total rise and fall is 4,350 feet. For the above undesirable reasons this route was not given further consideration.
Alignment C, 31.4 Miles
This route continues north from Warrensburg along the east bank of the Schroon River to South Horicon and up the valley to Brandt Lake; then north about a mile east of and parallel to Schroon Lake, coming into the Schroon River valley at Severance; then north to Schroon Falls.
This route is the shortest of all the alternates studied and will offer adequate service to the present developments and expected future expansion without infringing on expensive right-of-way.
This route also has a maximum elevation of 1,170 feet and only about two miles of highway at an elevation of over 1,000 feet. This alignment results in only two miles of grades over 3 percent with about 1 3/4 miles at 5 percent.
There would be a total length of about four miles of cuts and fills exceeding 20 feet. Total rise and fall is 3,230.
Comparing Alignment “C” factors which indicate the former and Alignment “B” there are several is the more desirable of the two.
1. It is six-tenths of a mile shorter which will reduce somewhat the initial investment, the maintenance expense and operation costs.
2. It has less miles at high elevations which lessen the hazards of winter driving and reduce maintenance costs.
3. There are fewer heavy cuts and fills which lower the initial construction cost and reduces maintenance.
4. There are fewer steep grades which will reduce operational costs and result in a safer highway.
5. The right-of-way costs will be less because the route traverses through less developed property.
6. Duplication of facilities will be minimized. The traffic along the west shore of Schroon Lake will still have touring Route 9 for local service.
Average estimated traffic on the Interstate Route, 1956 = 3,100 AADT [Annual Average Daily Traffic]; 1976 = 6,700 AADT.
Illustration: Cover of the NYS Department of Public Works Report Proposing The Adirondack Northway Interstate 87 Route through Forest Preserve – (Ticonderoga Historical Society – New York Heritage Digital Collections); Northway (I-87) at Lake George, ca. 1967; The Northway above Lake George, as portrayed by the Lake George Mirror, ca. 1967; a map showing proposed routes from thee Public Works report.

Fascinating to read this study again, from 1957 – two years later the Northway and the use of 400-acres of Forest Preserve for the Northway was approved by the voters. As we know, Alignment C was not chosen, despite its stated advantages. A modified Alignment B was chosen in spite of its stated disadvantages cost wise. One of those influencing the state’s choice of B, and not C, was Adirondack conservation leader Paul Schaefer who protested any highway ruining the potential of a future Pharaoh Lake Wilderness. As the schematic shows, C would have run east of Schroon Lake and through what is State Land Forest Preserve and part of Pharaoh Lake Wilderness. C would also have destroyed Horicon’s hamlet, town hall.
If I recall correctly, Northway was not quite finished for the opening of expo67 in Montreal. In Summer of 1967, we had to leave I-87 at Warrensburg … follow US 9 … and re-enter Northway at Willboro exit (Jct 9&22)., thus bypassing the areas being blasted to accommodate the new highway. — In Quebec, Autoroute 15 was incomplete. Northbounders followed Provincial Route 9 and then joined the 15. Southbound lanes were complete to the Border. Thanks for the trip down memory lane!
Aside: Plattsburgh AFBase opened 1955. With no Interstate and NO pipeline, jet-fuel was barged up Lake Champlain. The fuel-storage site is now a brownfield and cannot be used for residences, BUT has been developed into a vistor site for the Battle of Valcour (11~13 OCT 1776) Memorial, on US Route 9 just S of the City of Platssburgh. … Don’t drive by … Stop and vsit!