This summer, the Ausable River Association (AsRA) will undertake the second phase of construction in its Ausable River East Branch Restoration Program with Project Area 2 in Upper Jay, in the Adirondack Park in Essex County. This comprehensive program, developed in 2019 with funding from the Governor’s Office for Storm Recovery (now the Office of Resilient Homes and Communities), identifies 13 sites in the Town of Jay in need of restoration. Completing these river restoration projects will improve flood resilience, protect communities and infrastructure, and restore habitat for the food web that supports our native brook trout.
Project Area 2 is upstream of the NYS Route 9N bridge in Upper Jay and includes approximately 3,000 feet of river with eroding banks that have left it with an overly wide channel. Typical of many of the degraded sections of the East Branch Ausable River, the over-wide channel lacks the energy to move sediment because water is spread too thinly across it. Sediment builds up in the middle of the channel in seasonal floods and leads to more bank erosion as water is directed away from the center towards eroding banks, a self-perpetuating cycle. The widening channel threatens the primary transportation artery – Route 9N – and exacerbates the formation of damaging ice jam floods.
AsRA’s solution, developed with the US Fish and Wildlife Service (USFWS) and Ecosystem Planning and Restoration, a national leader in self-sustaining restoration design, is to mimic resilient rivers with stable banks that withstand moderate flooding with little damage. Using natural materials rather than concrete and blasted stone, the contractor is expected to build a bench along the eastern riverbank made of wood, river sediment, and coconut fiber fabric to shift the river channel away from the road, breaking the cycle of erosion while stimulating food webs for brook trout.
Native boulders are expected to be arranged through this section of the river to direct flows away from the banks, maintain the slope of the channel, and preventing the buildup of sediment that smothers life and destroys the structure of fish habitat. By improving the river’s ability to move sediment, it’s believed this design will also enhances the river’s ability to break up ice jams.
A similar design was used downstream at Project Area 3, behind the former Upper Jay schoolhouse, two years ago. It was tested by the ice jam in March 2022. Advocates for the plan say the design performed as expected as ice slabs rapidly broke apart and moved into storage on the constructed benches.
With an anticipated start date of early-July, the project is expected to be completed in six to eight weeks. The work is being funded by the NYS Department of Environmental Conservation-Water Quality Improvement Program, the New England Interstate Water Pollution Control Commission (NEIWPCC) through the Lake Champlain Basin Program (LCBP), and from the USFWS.
AsRA will hold a program on Wednesday, June 7th at the Town of Jay Community Center in Au Sable Forks, where Stream Restoration Manager, Gary Henry will be available to answer questions about this project and future projects in the East Branch Restoration Program.
For more information, visit the AsRA website.